WASHINGTON — BP aims to permanently seal the ruptured Gulf of Mexico oil well in the second week of September, a US official said Thursday, as pressure concerns further delayed final “bottom kill” operations.

“We should be looking somewhere in the week after Labor Day,” US spill chief Thad Allen said, referring to the September 6 US national holiday.

The ruptured Macondo well was capped on July 15 and earlier this month BP engineers performed a “static kill” which plugged it with heavy drilling fluid and then sealed it with cement.

However, there is an area behind the well and the outer well bore called the annulus which must still be sealed off from the reservoir miles below the surface of the Gulf of Mexico.

A relief well has been drilled and is poised to intercept the stricken well but experts are concerned that drilling into the annulus could lead to pressure problems at the top of the well.

After days of tests, Allen said they had agreed the best course of action is to replace the giant blowout preventer valve with a new one.

Allen said BP would start by “flushing out the current blowout preventer.

“Then (we will) actually move to put a new blowout preventer on, and then do the ‘bottom kill.’ This will ensure that we can withstand any pressures that may be generated.”

Allen and BP had originally pointed to mid-August as the target date for shutting down the Macondo well once and for all, although Allen had until Thursday declined to give a new timeline as that deadline passed.

Two storms in the Gulf -- one in late July and another in mid-August -- delayed by several days the drilling of the relief well.

Allen vowed to finish the job, saying: “We’re making sure that we put a stake in the heart of this monster.”

“We’ve been working a week and a half with BP on a way forward and I have been equivocating on the timeline for a good reason, because we needed to take concrete steps to kill this well.”

Acadia Parish Today

Crowley Post-Signal
P.O. Box 1589, Crowley, LA 70527
Phone: 337-783-3450
Fax: 337-788-0949

Rayne-Acadian Tribune
P.O. Box 260, Rayne, LA 70578
Phone: 337-334-3186
Fax: 337-334-8474

Church Point News
315 N. Main St., Church Point, LA 70525
Phone: 337-684-5711
Fax: 337-684-5793

Follow Us